Sunday | Monday | Tuesday | Wednesday | Thursday | Friday | Saturday |
---|
27 | 28 | 29 | 30 | 31 | 1
S ELECT CONDUIT
SOUTH SEWER SET SOUTH SEWER INSP
SEWER LINE BACKFILL FINAL ROCK BACKFILL
ENTRY PINE CANYON
BACKFILL ASSIST
WALK AREA DRAINS
| 2
|
3
| 4
BACKFILL INSPECTION
PINE CANYON ENTRY
DIRT BACKFILL SOUTH AREA DRAINS
SOUTH DIRT GRADE
BACKFILL ASSIST
SECURITY FENCING
| 5
GENIE PARTS ORDER
PINE CANYON S STEP
DIRT BACKFILL MISC
ENTRY SWALE GRADE
DEER WALK GRADE
BACKFILL ASSIST
NORTH D SPOUT PIPE
NORTH AREA EXTEND
| 6
SOUTH SCAFFOLD
SOUTH SHEER PLY SOUTH SHEER NAIL SITE ORGANIZE
| 7
WINDOW RAIN COVER
BRIDGE LAYOUTS
BRIDGE JOISTS
MASTER SCAFFOLD SITE CLEANÂ MISC
| 8
ARCHITECT MTG ENGINEER MTG
RAIN READY
BRIDGE JOISTS
BRIDGE BLOCKING BRIDGE TEMP PLY BEAM TEMP CUTS
| 9
|
10
| 11
RAIN
BRIDGE SCAFFLD OUT
BRIDGE CLIP ROUTER
BRIDGE CLIPS
| 12
UPPER SAFTY RAILS
UPPER FRAME SHOP
2ND FLOOR LAYOUT
ENTRY BEAM CUTS
| 13
MATERIAL DELIVER
SND FLOOR LAYOUTS
2ND FLOOR CUTS
2ND FLR FRAME START
| 14
2ND FLR FRAME CUTS
2ND FLOOR FRAME N
| 15
2ND FLR FRAME CUTS
2ND FLOOR FRAME W FIREBLOCKING
LAYOUT EAST WALL CUTS EAST WALL
SOLAR MTG | 16
WEEK SUMMARY RAIN PREP MISC
RAIN MONDAY
FIRE DOOR ORDER
SOLAR MTG MISC
BRIDGE CLIP ROUTER MISC CLIPS SET ENTRY BEAM CUTS
UPPER SAFTY RAILS UPPER FRAME SHOP
2ND FLR FRAME START
2ND FLOOR LAYOUTS
2ND FLOOR FRAMING
FIREBLOCKING
|
17
| 18
EAST WALL CUTS
2ND FLR FRAME EAST BED 2 INT WALLS
| 19
BED 3 MAT ORDER
BED 2 INT WALL CUTS
BED 2 INT WALLS
BED 2 WALLS FRAMED
| 20
MATERIAL DELIVER
SHOP MOVE TO BED 2
MATERIAL MOVE
BED 3 WALL LAYOUTS
| 21
BRIDGE CLIPS
BED 3 LAYOUTS
BED 3 PLATES CUT
BED 3 WALL CUTS BED 3 FRAME START WALL FRAME NORTH
ELECT DESIGN PGE
| 22
SOUTH WALL CUTS
2ND FLR WALL SOUTH EAST WALL CUTS
2ND FLR WALL EAST
| 23
WEEK SUMMARY
RAIN FRI AFTERNOON RAIN FRIDAY NIGHT
PGE ELE DESIGN CALL
EAST WALLL CUTS EAST WALL FRAME BED 2 INT WALL CUTS
BED 2 INT WALLS
BED 2 WALLS FRAME
BED 2 FIREBLOCKING
UPPER SHOP MOVE
BRIDGE CLIPS SET
LAYOUT BED 3 BED 3 CUTS START
BED 3 START FRAME
BED 3 SOUTH WALL BED 3 EAST WALL
|
24
| 25
RAINÂ A.M. BSMNT MISC BLOCKING
3RD FLR WEST WALL INT WALL LAYOUTS
INT WALL CUTS
| 26
RAIN 1/2 DAY
INT BATH WALL INT CLOSET WALL
WAlll FIREBLOCKING | 27
FIREBLOCKING
UPPER WALL BRACING WALLS PLUMB & LINE
MATERIAL ORDER
| 28 HOLIDAY
| 29
FIREBLOCK FINISH
2ND FLOOR P&LINE STAIRWALL LAYOUTS
TERRACE 1/2 WALL
| 30
WEEK SUMMARY RAIN MONDAY A.M. RAIN TUES A.M. BASEMENT BACKING GARAGE FORM OUT
WEST BALCONY WALL
INTERIOR WALL CUTS INTERIOR WALLFRAME
FIREBLOCKING
WALL BRACING
WALLS PLUMB & LINE
STAIRWELL LAYOUTS
|
1 | 2 | 3 | 4 | 5 | 6 | 7 |